KPC Responds to Pipeline Puncture Near Tassia in Nairobi
The Kenya Pipeline Company (KPC) has deployed emergency response teams after a contractor punctured its Mombasa–Nairobi pipeline during drilling works near Tassia, Nairobi.
The incident occurred at approximately 9:00am on Line 5, which transports petroleum products from Mombasa to Nairobi. The affected pipeline section runs near Outer Ring Road in Embakasi Central Sub-County.
KPC said preliminary assessments point to a contractor engaged by the Kenya Railways Corporation (KRC). The contractor was conducting geotechnical surveys and drilling when the incident occurred.
KPC Activates Emergency Response
KPC quickly mobilized its technical and emergency response teams after receiving notification of the incident. The teams shut down the affected pipeline section to contain the product release and secure the area.
The company also deployed its Incident Management team, pipeline repair personnel and fire-safety teams.
Mr Mwendwa said the company had brought the situation under control.
“The situation is under control,” he said.
He added that investigations were underway. The KRC drill rig operators were assisting the Kenya Police Service with the investigations. Meanwhile, KPC’s technical teams were assessing the damage and preparing the necessary repairs.
KPC has also cordoned off the affected area. Additional personnel and equipment are supporting product containment, recovery and environmental management.
Investigations and Repairs Underway
KPC is working with security and emergency response agencies to manage the incident and limit its impact.
Its technical teams are assessing the extent of the damage and undertaking the required repairs. They are also overseeing product recovery and measures to protect the surrounding environment.
The company said it prioritizes the safety of communities living near its infrastructure. It also remains committed to protecting the environment and maintaining the integrity of its pipeline network.
KPC will continue containment and recovery operations. The company also plans to restore the affected area in line with applicable safety and environmental standards.
More related reads can be be found here